Take note of the following if you would like to submit building plans, civil and structural plans, or mechanical and electrical plans. You are required to submit the building plan to the Building and Construction Authority/ Fire Safety & Shelter Department.
Here are the various stages of the submission process:
Stage of Submission
HDB (ARCH)
HDB (C&S)
HDB (M&E)
Building plan
Technical clearance of building plans
Technical clearance of civil and structural plans
Technical clearance of mechanical and electrical plans
Temporary Occupation Permit
N/A
Technical clearance of civil and structural as-built plans
Technical clearance of mechanical and electrical works
Certificate of Statutory Completion
Compliance certificate
Building plan:
Addition & Alteration (A&A) plan:
We must approve C&S plans before they are submitted to the Building and Construction Authority and/ or the Fire Safety and Shelter Department.