Replacement of existing sink with stainless steel/enamelled type and wash basin with coloured type
| Not applicable. |
Reposition of kitchen sink supported by 63mm thick hollow walls with tiles finishes
|
- Thickness of dapoh slab inclusive of finishes should not exceed 50 mm.
- Floor slab must not be tampered with.
|
Repositioning of sink/wash basin
|
- Floor slab must not be tampered with.
|
Installation of shower screen
|
Replacement of existing PVC pipe with copper/stainless steel pipe
| Not applicable. |
Re-diversion of sink waste pipe
|
- Pipe must not be embedded in floor slab.
- Pipe is allowed to be embedded within floor finishes.
|
Enclosure/encasement of service ducts/pipings (excluding gas pipe) using lightweight non-combustible materials
|
- Need to provide minimum removable access opening of 600 mm x 600 mm for inspection and maintenance.
|
Enclosure/encasement of gas riser pipe using lightweight non-combustible materials
|
- Need to provide a fully ventilated removable access (600 mm width and full height from ceiling to floor) for inspection and maintenance of gas riser pipe.
Points to note:
- All gas riser pipes including riser branch pipe (before sub-meter) must not be tampered with.
- All gas pipes must NOT be embedded in the common partition walls.
- Gas Pipes are NOT allowed in bedrooms. Space with gas pipes are therefore not allowed to be converted to bedrooms.
- All gas pipe alteration works must be carried out by City Gas Pte Ltd or a Licensed Gas Service Worker.
|
|
|
- Works must be carried out by City Gas Pte Ltd.
- Need to comply with SCDF’s guidelines.
|
Removal of gas branch pipe (after sub-meter)
|
- A 100 mm length of gas pipe protruding from the wall into the kitchen must be maintained and capped when not in use.
- Works must be carried out by City Gas Pte Ltd or a Licensed Gas Service Worker.
|
Concealed waste/water pipes in floor finishes/wall
|
- Floor slab and wall must not be tampered with.
|
Concealing air-conditioner discharge pipe in floor finishes
|
- Floor slab must not be tampered with.
- The pipe must be concealed within the floor finishes only.
|
Installation of long bath
|
- Void area beneath long bath is not allowed to be filled with cement mortar or anything. There must be a void beneath.
- Provide inspection opening for future maintenance.
- Floor slab must not be tampered with.
- Extension of toilet to accommodate the long bath is not allowed.
|
Installation of shower tray
|
- Void area beneath shower tray is not allowed to be filled with cement mortar or anything. There must be a void beneath.
- Floor slab must not be tampered with.
|
Replacement of squat pan with new squat pan or pedestal pan with new pedestal pan
| Not applicable. |
Installation of pedestal/squat pan at wash area on lower floor of executive maisonette
|
- Hacking of holes on the existing floor slab is not allowed.
- The installation details for pedestal pan shall be in accordance with the sketch in the A & A guidelines.
- The installation details for squat pan shall be in accordance with the sketch in the A & A guidelines.
|
Replacement of squat pan to pedestal pan
|
- Hacking of holes on the existing floor slab is not allowed.
- The installation is to follow the sketch according to A & A guidelines (see sketch Drawing 5).
|
Replacement of pedestal pan to squat pan
|
- Hacking of holes on the existing floor slab is not allowed.
- The minimum ceiling height from this finished raised floor slab should not be less than 2.2 metres.
- The installation is to follow the sketch according to A & A guidelines (see sketch Drawing 6).
|
Removal of surface-run water pipes
|
- Compliance with PUB's requirements.
- Engage a Licensed Water Service Plumber for the works.
|
Removal of surface-run portion of the concealed hot and cold water pipes
|
- Compliance with PUB's requirements.
- Engage a Licensed Water Service Plumber for the works.
- The pipes are to be terminated with compression fitting capping with at least 50 mm length protruding from the wall.
|
|
|
- SPA pool must be purchased ready-made from the market.
- Construction of SPA pool using bricks/hollow blocks is not allowed.
- SPA pool is to be installed only within bathroom/toilet originally provided by HDB.
- Total weight inclusive of SPA pool, water, motor and other accessories must not exceed 400 kg.
- Floor slab must not be tampered with.
- Provide proper water drainage for SPA pool.
|
Installation of gas water heater/gas oven
|
- Compliance with City Gas Pte Ltd's requirements.
- Engage a Licensed Gas Service Worker (LGSW) for the works.
- Outdoor installation is subject to HDB's approval.
|