Application of Conversion Scheme for Resale Flat
 

Before committing to the purchase of an adjoining flat, you shall:
  • Request HDB to check whether the pairing of flats is possible and
  • Mode of financing

Read more about the purchase of resale flats under Conversion Scheme:

Procedure to Apply

Below is the step-by-step guide to the procedures involved:

1Get the application form, "Scheme for Conversion of 3-Room or Smaller Flat" from:
    The Resale Operations Unit
    Atrium 1st floor
    HDB Hub
    480 Lorong 6 Toa Payoh

2Complete the application form and submit it to the Resale Operations Unit.

3HDB will check whether the pairing of flats is possible.


Financing

Type of Housing Loan

The purchase of an adjoining flat can be financed with
Under the HDB Loan, HDB will give a loan of up to 90% of whichever is lower:
  • Market value, or
  • Declared resale price of the adjoining flat
In addition, the loan amount is also subject to credit assessment and full utilisation of the buyers' CPF savings in their Ordinary Accounts.


Conditions for Switching Housing Loan

If you are changing your mode of financing for the purchase of the adjoining unit, you must make sure that the outstanding mortgage loan for your existing flat has been discharged.

Example 1 : Existing flat is financed with an HDB/bank loan. The adjoining flat is to finance with another bank loan

You must:
  • Check with the bank on the total loan amount available for discharge of the outstanding mortgage loan and for the purchase of the adjoining flat.
  • Ensure that the outstanding HDB/bank loan of your existing flat has been discharged before purchasing of the adjoining flat.


Example 2 : Existing flat is financed with a bank loan. The adjoining flat is to be financed with an HDB loan

You must:
  • Consult your bank on the procedures involved in discharging the outstanding mortgage loan for your existing flat.
  • Ensure that the outstanding bank loan has been discharged before purchasing of the adjoining flat.
HDB loan financing is only for purchase of the adjoining flat and not for the discharge of bank loan.


Conversion of Flats

On completion of purchase, you must convert the two adjoining flats into one unit by:

What you need to doWho you shall engageThe change is...
Constructing at least an opening (1meter x 2meters) between the 2 units Registered renovation contractor

Need to apply renovation permit from HDB before the work.
Mandatory
Removing one each of the PUB meters for electricity, water and gas supplyLicensed contractorMandatory
Making good the electrical sub-mains outside the flats after removal of the PUB meterHDB term contractorOptional
Carrying out re-wiring Licensed electrical contractor*

Need to apply for approval from Power Supply Pte Ltd before the work.
Optional
Carrying out water re-piping Licensed plumber*

Need to apply for approval from PUB Water Department before the work.
Optional
Carrying out gas re-piping Licensed gas service worker*

Need to apply approval from Power Supply Pte Ltd before the work.
Optional
* Can also engage Power Supply/PUB to carry out the work.


You shall retain the existing flat number for the combined flat


Conditions for selling the Converted Flat

You can sell your converted flat:
If your original 3-room or 2-room flat was bought directly from HDB, you will be:
  • Treated as having sold a flat, and
  • Required to pay the resale levy

If your original 3-room or 2-room flat was your second flat bought directly from HDB, you will be debarred permanently from buying another flat from HDB.

You cannot sub-divide the converted flat into two flats to sell, transfer, surrender, etc.


Payment of Upgrading Cost for Main Upgrading Programme (MUP)

If the completion of purchase is during/after MUP polling

You are required to pay for the upgrading costs based on the sum total of the two original flat types

As each Singapore Citizen household is only allowed to enjoy one upgrading subsidy, the subsidy for the second flat will be reduced even if you have not enjoyed an upgrading subsidy previously.

In addition, if the precinct has voted in favour of the Standard Package plus Space-adding Item, you will be required to pay for the 2 additional space-adding items. Read more about the type of upgrades under MUP.

If the completion of purchase is before MUP polling

You are required to pay for the upgrading costs based on the redesignated flat type.

Last Updated on 26 Aug 2010